Case History
 
Back to Case Studies
     
 

Hayes Data Centre

Date: 2007

Location: Hayes Middlesex

Project: Data Centre

Sector: Banking

End Client: Large Merchant Bank 

Project Team Principles:
Cundall / ISG / MJ Lonsdale

Value: >£100k

System: Trend IQ2/963
Control I/O: 150+
Panels: 1 MCC, 12 Monitoring Panels

Plant / Services:
Standby Generators
Electrical Switchgear
Static UPS
Pod Cooling AHU’s
CRAC Units (DX Close Control)
General Supply / Extract AHU’s

Notable / Special Features:
Very Fast Track Project,
Design and Build Type Project,
Existing Critical Services Maintained Throughout Project

Project Overview:

The data centre was provided to the end client by a multi-disciplinary project team, working within a very fast track project brief.

Orlanix developed, designed, installed, and commissioned, the Building Management System for the main IT data suite, and associated roof plant areas; based on the requirements of the project performance specification, ongoing design changes, and enhancements.

The primary function of the BMS is to monitor the buildings critical power, environmental, and life safety, systems.

In addition the BMS carries out control functionality for a number of environmental systems; such as fresh air supply, and extract, and provides basic control interfaces with a number of buildings OEM control systems.

 